The Cost-Influence Curve — Why "We'll Optimise It in Detailed Design" Is Already Too Late
The meeting where it is always too late
Week 31 of detailed design. You are looking at a 3D model review and you can see it plainly: the maintenance access to the pump house is blocked by a rack bent, the two spare pumps nobody will ever run are eating 11 m of plot, and the 316L line spec that Process wrote for a "possible future sour case" runs 340 m of 6″ pipe that will never see a chloride.
You raise all three. The project manager says the sentence that this note exists to kill:
"Good catch — we'll optimise it in detailed design."
You are in detailed design. And here is the question: what fraction of this project's total lifecycle cost do you think is still genuinely available to be optimised right now? Guess before reading on. Most engineers say 40–60 %.
The answer is roughly 5–7 %. By the time detailed design opens, about 80 % of lifecycle cost is already committed — while only about 3 % of the money has actually been spent. That gap between committed and spent is the single most useful idea in project engineering, and almost nobody is taught it.
The curve: committed runs far ahead of spent
Two curves live on the same time axis, and confusing them is the whole misconception.
Committed cost C(t) — money the project is now OBLIGED to spend, because of decisions taken
Expenditure S(t) — money that has actually LEFT the bank
Influence I(t) = 100 % − C(t) (what you can still change without paying to undo)
- C(t) is a cliff. It rises almost vertically through FEL and FEED, then flattens.
- S(t) is a slow S-curve. It stays near zero through the whole front end and only takes off when steel, valves and construction hours start being paid for.
Typical industry shape (the numbers the interactive uses):
| Milestone | Committed | Spent | Influence left |
|---|---|---|---|
| End of concept / FEL-1 | 40 % | 0.5 % | 60 % |
| End of FEED / FEL-3 | 80 % | 3 % | 20 % |
| End of detailed design | 93 % | 12 % | 7 % |
| Start of construction | 97 % | 35 % | 3 % |
Read the FEED row again. The cheque book still looks almost untouched. That is exactly why the illusion survives: everyone confuses "we have barely spent anything" with "we can still change anything." They are not the same statement. The second one stopped being true long before the first.
Watch the two surfaces trade places — the committed landscape is a cliff at the near end, the expenditure landscape is a cliff at the far end, over the same axes: ▶ open the interactive: project cost influence 3d
Why commitment leads expenditure by so much
Commitment is created by decisions that constrain later decisions, and those are all made early because everything downstream needs them as input. Choose 120 % design capacity and you have chosen every vessel diameter, every pump curve, every line size and every kilowatt of utilities that follow — before a single purchase order exists. The PO, months later, is not the decision; it is the settlement of a decision already made.
The practical consequence is that the "cost" of a late change is rarely the new scope. It is the cost of undoing work that was entirely correct against the previous basis: engineering hours already spent, drawings already issued, material already bought to the old spec, foundations already poured, and the schedule float already consumed. A 6″ line that was correct in Rev 0 and correct in Rev 3 is still a full re-run of hydraulics, stress, supports, MTO and isometrics if the basis moves under it.
What actually locks the cost — and when
Not all decisions are equal. These seven commit most of the lifecycle cost, roughly in the order they close:
- Capacity and margin philosophy — the single biggest lever. "Design for 120 % of nameplate" sizes every downstream item. Locked at concept.
- Sparing philosophy — 2 × 100 % vs 3 × 50 % vs 1 × 100 % + shelf spare. Locked at concept/FEED. Drives equipment count, plot, power, and 25 years of maintenance.
- Plot layout — distances become pipe, cable, rack steel, and civil. Locked at FEED.
- Spec class / design codes — flange ratings, corrosion allowance, NDE extent, the piping class matrix. Locked at FEED and very expensive to reopen.
- Equipment selection — vendor, type, materials, driver. Locked FEED → procurement.
- Materials of construction — CS vs 316L vs duplex vs lined. Locked at FEED, settled at PO.
- Automation level — loop count, SIL targets, DCS vs local. Closes latest of the seven, and is the one a discipline engineer can still genuinely influence in early detailed design.
The 3D landscape plots exactly this: phase × decision area, height = committed. Slide the marker across and you can see that the "cliff" happens at a different place for each row — capacity is already a wall at concept, automation still has a slope at detailed design. That slope is where your remaining leverage lives.
Symbol key — every symbol on this sheet
- C(t) — committed cost: fraction of lifecycle cost the project is now obliged to spend · %
- S(t) — expenditure: fraction of lifecycle cost actually paid out · %
- I(t) — influence remaining = 100 % − C(t) · %
- M — change-cost multiplier: cost of a change now ÷ cost of the same change at FEED · ×
- FEL — Front-End Loading; FEL-1 concept, FEL-2 selection, FEL-3 = FEED · phase
- FEED — Front-End Engineering Design, the last cheap phase · phase
- IFC — Issued For Construction (the drawing revision the site actually builds to)
- TIC — Total Installed Cost (capex as built, excluding operating life)
- LCC — Life-Cycle Cost: capex + energy + maintenance + downtime over the asset life
- VIP — Value Improving Practice (a structured front-end workshop, e.g. Value Engineering, Design-to-Capacity, Process Simplification)
- MOC — Management Of Change (the formal gate a change must pass after a basis is frozen)
Where "80 %" comes from, and how much to trust it
The curve is a shape, not a measurement. Its lineage runs through Paul Barshop's and Ed Merrow's work at IPA (Independent Project Analysis) on front-end loading, the CII (Construction Industry Institute) Pre-Project Planning research, and AACE International's cost-estimate classification (Class 5 → Class 1). The consistent empirical finding across those data sets is not the exact number 80 % — it is the correlation: projects with poor front-end definition at sanction overrun cost and schedule far more often than well-defined ones, and the penalty is measured in tens of percent, not single digits.
So quote the shape with confidence and the number with care. "Most of the cost is committed before detailed design starts, and the projects that get the front end right are the ones that land on budget" is defensible everywhere. "Exactly 80 % at exactly the FEED gate" is a teaching figure, and the true value depends on scope, contracting strategy and how much is repeat design.
The 1 : 10 : 100 escalation — worked in money
The classic rule of thumb: a change caught in design costs 1; in procurement/fabrication about 10; in construction/commissioning about 100.
Cost of change = base cost at FEED × M(change type, phase)
Worked example — the pump house that was 8 m out of position. Base cost of making this change during FEED: $4,000 (a redrawn plot plan, a re-run of the suction hydraulics, two revised P&ID clouds, 40 engineering hours).
| Raised in | M | Cost | Schedule |
|---|---|---|---|
| FEL-3 FEED | 1 × | $4,000 | none |
| Detailed design | 11 × | $44,000 | ~2.5 days |
| Construction | 105 × | $420,000 | 3 weeks |
At construction you are paying for: demolishing two poured foundations, cutting and re-fabricating twelve spools, re-running the stress analysis and the support MTO, re-issuing twelve isometrics, re-routing a cable tray, re-scheduling a crane, and re-testing the system. The change is still 8 m. Everything else on that invoice is undoing work that was correct.
1 : 11 : 105. The rule of thumb is not an exaggeration; if anything it is gentle, because it counts only direct cost and not the delay.
Pick your own change type and phase and watch the multiplier, the schedule hit and the remaining influence move together — the bar chart is on a log scale precisely because a linear one cannot show 0.1 × and 320 × on the same picture: ▶ open the interactive: project cost influence calc
Where a discipline engineer's leverage actually sits
Your leverage is not proportional to your seniority. It is proportional to how early you speak. The same observation, made by the same person, is worth roughly 100 × more in FEED than in construction — and it costs you the same amount of effort either way.
Three things to actually do:
- Flag interface risk in FEED, in writing. "Piping cannot route this line without a 4 m loop unless the exchanger moves 2 m" is a $0 sentence in FEED and a $200k sentence in construction. Put it in the FEED deliverable comments, not in a corridor.
- Challenge margin and spec class — with a number. "Why 316L on this service?" is ignored. "316L on this service is 340 m of 6″ at roughly 4 × the CS material cost; the sour case it protects against is not in the design basis — can we hold CS with 3 mm CA?" gets a decision. Margins stack multiplicatively: a 10 % process margin on top of a 10 % equipment margin on top of a 10 % line-sizing margin is 33 % of oversized plant nobody chose.
- Insist on constructability and maintainability review before IFC. IFC is the point where the cost of change steps from ~10 × to ~100 ×. A two-hour review with a construction superintendent and a maintenance planner before that step is the highest-yield meeting on any project. Ask for lay-down, crane access, bolt clearance, valve reach and tube-bundle pull space explicitly — those are the four things that get discovered on site.
And know the counter-argument so you can answer it: front-end work is not free either. FEED typically costs 2–5 % of TIC, and a gate held open forever has its own cost. The argument is never "spend unlimited time in FEED" — it is "spend the right time there, because the exchange rate is 100 : 1 and it only runs one way."
Common pitfalls
- Confusing "barely spent" with "still flexible." The two curves are not the same curve. This is the misconception in one line.
- Treating the FEED gate as a paperwork milestone. The gate is where influence collapses; the deliverables list exists to make sure the collapse happens with your input in it.
- Optimising a line, not a decision. Saving 6 m of pipe is real; questioning a spare pump that costs 11 m of plot, a foundation, a starter, a cable and 25 years of PM is 100 × bigger.
- Raising an issue verbally. If it is not in a comment sheet or a minuted action, it did not happen and you will be told "why didn't you say something?" during the claim.
- Assuming the curve applies to every scope equally. Repeat/replicated designs and modularised scopes commit even earlier; a small brownfield tie-in with a flexible basis may keep genuine influence deeper into detailed design. Know which one you are on.
- Using the curve as a reason to stop looking. Finding the problem at 97 % committed is still cheaper than finding it at 99.5 %. Late is expensive; never is worse.
Outcome
- Ability to influence cost collapses through FEL/FEED while expenditure barely moves; by the start of detailed design roughly 80 % is committed and 3 % is spent, leaving ~20 % influence — and ~5 % by the time the model is built.
- What commits cost early: capacity/margin philosophy, sparing, plot layout, spec class, equipment selection, materials of construction, automation level — roughly in that order.
- Cost of change escalates about 1 : 10 : 100 across design : procurement : construction. Worked: the same 8 m pump-house move is $4k in FEED, $44k in detailed design, $420k plus three weeks in construction.
- Your leverage as a discipline engineer is a function of when you speak, not how loudly: flag interface risk in FEED in writing, challenge margins with numbers, and force a constructability review before IFC — the step where 10 × becomes 100 ×.
- Interactive: ▶ open the interactive: project cost influence calc — change type × phase → multiplier, cost, schedule hit, influence remaining, plotted on the live curves.
- 3D: ▶ open the interactive: project cost influence 3d — commitment landscape over phase × decision area; toggle to the expenditure surface and watch the cliff move to the other end.
Open items
- Calibrate the multiplier table against real project change-order data (our own MOC log) rather than the generic 1 : 10 : 100 shape.
- Add a contracting-strategy dimension: EPC lump sum, EPCM reimbursable and converted lump sum commit cost at visibly different points, and the curve should show it.
- Worked FEED-gate deliverable checklist for piping/stress specifically — what has to exist at the gate for our discipline's influence to actually be captured.
One sheet from EPiC Circle
Interactive engineering lessons across every EPC discipline — calculators, 3D models and misconception-first teaching. Free to read; sign in to track progress, take the quizzes and ask questions.
Open in EPiC Circle →Educational teaching material — simplified and illustrative. Not for engineering
design use.
© EPiC Circle · provided by PipeAxis