Critical-Path Playground 7 ACTIVITIES · DRAG A DURATION · WATCH THE PATH MOVE

ACTIVITY DURATIONS (WORKING DAYS)

43DAYS — PROJECT DURATION

ActivityDurESEFLSLFTFFF

TF = LS − ES, slip before the project moves. FF = earliest successor ES − EF, slip before the next activity moves. FF ≤ TF always.

DELAY INJECTION — WHO ABSORBS IT?

Educational teaching tool — simplified and illustrative. Not for engineering design use.