ACTIVITY DURATIONS (WORKING DAYS)
43DAYS — PROJECT DURATION
| Activity | Dur | ES | EF | LS | LF | TF | FF |
|---|
TF = LS − ES, slip before the project moves. FF = earliest successor ES − EF, slip before the next activity moves. FF ≤ TF always.
DELAY INJECTION — WHO ABSORBS IT?